Question 7 (Volume A)

The Project Communications Management knowledge area focuses on which of the following processes?

Each correct answer represents a complete solution. Choose all that apply.

Select all that apply, then click Submit answer.

  • Identify Stakeholders

  • Distribute Information

  • Create Work Breakdown Structure (WBS)

  • Report Performance

Question 8 (Volume B)

You have recently started a project and assembled the project team which has begun working on the project. However, recently, a project team member has expressed his concerns of having issues with one of the other project team members, and cannot get him to collaborate. What is the MOST appropriate activity for you to do in this scenario?

Select an option, then click Submit answer.

  • Meet with both team members, assess the scenario, and be more directive in decision mak ing.

  • Replace the other project team member immediately with another suitable resource.

  • Reallocate both team members different works so that there is no overlap, by resolving the chance for conflicts.

  • Update your PMO about the conflict and raise a project risk about team disruption.

Question 9 (Volume B)

At which of the following points in a project lifecycle is the level of uncertainty and risk the highest?

Select an option, then click Submit answer.

  • Planning

  • Closing

  • Beginning

  • Monitoring