During the Execution phase, a Stakeholder calls the Project Director to request a product feature not part of the Project Plan. The Product Director asks the Project Manager to add the information to what type of document to accommodate the Stakeholder?
Select an option, then click Submit answer.
-
○
Project Enhancement Record
-
○
Feature Request Document
-
○
Issue Log Document
-
○
Project Plan