Question 13 (Volume B)

A project team member agrees to change a project deliverable after a conversation with an external stakeholder. It is later discovered that the change has had an adverse effect on another deliverablE. This could have been avoided if the project team had implemented:

Select an option, then click Submit answer.

  • Quality assurancE.

  • A stakeholder management plan.

  • Project team buildinG.

  • Integrated change control.

Question 14 (Volume C)

The scope management plan is a subsidiary of which project document?

Select an option, then click Submit answer.

  • Schedule management plan

  • Project management plan

  • Quality management plan

  • Resource management plan

Question 15 (Volume E)

An input to the Estimate Activity Resources process is:

Select an option, then click Submit answer.

  • Activity resource requirements.

  • Published estimating datA.

  • Resource calendars.

  • Resource breakdown structure (RBS).