Question 4 (Volume D)

Identify the missing word in the following sentence. The guiding obligations and good practices which determine whether the project is genuinely being managed using PRINCE2 form the [ ? ] of the method.

Select an option, then click Submit answer.

  • Principles

  • Themes

  • Processes

  • Techniques

Question 5 (Volume A)

Which role is responsible for the management of a risk assigned to it?

Select an option, then click Submit answer.

  • ProjectSupport

  • Risk owner

  • Risk actionee

  • Project Assurance

Question 6 (Volume B)

A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?

Select an option, then click Submit answer.

  • Raise a request for change

  • Raise an off-specification

  • Write an Exception Report