Question 1

Which occurs when the P3O implementation programme is closed?

Select an option, then click Submit answer.

  • Vision Statement is refined to reflect delivery

  • Blueprint is produced to document processes

  • Risks to the implementation are captured

  • P3O capability becomes business as usual

Question 2

Which functional area considers risk against the ability to achieve planned outcomes for a specific business change?

Select an option, then click Submit answer.

  • Strategic planning/portfolio support

  • Delivery support

  • Project

  • COE

Question 3

Which is a common barrier to be overcome when agreeing a mandate for a P3O?

Select an option, then click Submit answer.

  • Carrying out P3M3 assessments

  • Agreeing the measures to be used to prioritize the portfolio

  • Agreeing the funding model for a P3O

  • Documenting processes via business process swimlanes