Question 1

What is bottom-up scheduling?

Select an option, then click Submit answer.

  • Team members representing each role generate time estimates and schedules for deliverables. Each team schedule is integrated into aTeam members representing each role generate time estimates and schedules for deliverables. Each team? schedule is integrated into a master project schedule.

  • The program manager estimates the time required for each team member to complete his or her tasks, and then validates those estimates with the team members.

  • The program manager builds a master project schedule based on industry standards for each task.

  • The solution manager estimates the time required for each team member to complete his or her tasks, and then validates those estimates with the team members.

Question 2

What does the focus of the Governance, Risk and Compliance SMF in the Plan Phase not include?

Select an option, then click Submit answer.

  • General regulatory environment

  • High-level risks

  • Investment determination

  • Internal controls defined

Question 3

To create an environment where changes can be made with the least amount of risk and impact to the organization this is the goal of which SMF?

Select an option, then click Submit answer.

  • Business/IT Alignment SMF

  • Change and Configuration SMF

  • Policy SMF

  • Stabilize SMF