EX0-008 Agile Scrum Foundation

Loading demo links...

Showing 7–9 of 10 questions

Question 7

A team is trying to convince a customer about the value of adopting Scrum. The customer likes some of the features of the methodology like the bi-weekly demonstration, but the customer remains largely unconvinced of the value of Scrum and refuses to change the way of working,

What should the team do?

Select an option, then click Submit answer.

  • Let the Scrum Master 'translate' to Waterfall practices.

  • Use Scrum and convince the customer during the process.

  • Do not follow Scrum until the customer is convinced of the value.

Question 8

A story was estimated at eight ideal hours. A working day is eight hours. Developers can get about six hours of work done on a daily basis.

What is the elapsed time required to complete the story?

Select an option, then click Submit answer.

  • 1.25 days

  • 1.33 days

  • 2 days

  • This cannot be determined without knowing the velocity.

Question 9

A team selects a Product Backlog Item (PBI) for the Sprint Backlog.

What must a team do to finish the Product Backlog Item it selects?

Select an option, then click Submit answer.

  • As much as can be done in the Sprint before the deadline.

  • As much as is required to satisfy the definition of 'done'.

  • Analyze, design, program, test and document the PBI.