Question 4

Which should be done during the process Closing a Programme?

Select an option, then click Submit answer.

  • Confirm that key stakeholders are satisfied with the improvements

  • Provide an opportunity to plan a post-project review

  • Identify the need for future assessment of benefit realization

  • Enable all outstanding risks to be closed

Question 5

Which is a reason for the process Closing a Programme?

Select an option, then click Submit answer.

  • Maintain alignment of supplier activity

  • Consolidate the Programme Definition

  • Monitor changes to corporate strategy

  • Provide feedback to corporate governance

Question 6

Which describes dependencies that are external to an organization's programme and project environment?

Select an option, then click Submit answer.

  • Part of the governance of the corporate portfolio

  • Within the control of the programme itself

  • Resulting from government decisions to change legislation

  • Resulting from relationships between the projects within the Projects Dossier