Question 4

Which should be done during the process Closing a Programme?

Select an option, then click Submit answer.

  • ○

    Confirm that key stakeholders are satisfied with the improvements

  • ○

    Provide an opportunity to plan a post-project review

  • ○

    Identify the need for future assessment of benefit realization

  • ○

    Enable all outstanding risks to be closed

Question 5

Which is a reason for the process Closing a Programme?

Select an option, then click Submit answer.

  • ○

    Maintain alignment of supplier activity

  • ○

    Consolidate the Programme Definition

  • ○

    Monitor changes to corporate strategy

  • ○

    Provide feedback to corporate governance

Question 6

Which describes dependencies that are external to an organization's programme and project environment?

Select an option, then click Submit answer.

  • ○

    Part of the governance of the corporate portfolio

  • ○

    Within the control of the programme itself

  • ○

    Resulting from government decisions to change legislation

  • ○

    Resulting from relationships between the projects within the Projects Dossier