Question 4

Which should be funded by a change budget?

Select an option, then click Submit answer.

  • ○

    Increase in agreed scope

  • ○

    Initiation stage

  • ○

    Change Authority

  • ○

    Handover activities

Question 5

Which process provides the Project Board with the information it requires in order to commit

resources to the project?

Select an option, then click Submit answer.

  • ○

    Managing Product Delivery

  • ○

    Initiating a Project

  • ○

    Controlling a Stage

  • ○

    Directing a Project

Question 6

In what product should the quality criteria for a specialist product be recorded?

Select an option, then click Submit answer.

  • ○

    Quality Management Strategy

  • ○

    Quality Register

  • ○

    Product Description

  • ○

    Project Product Description