Free DES-1221 – Specialist - Implementation Engineer - PowerStore Solutions Exam Practice Test Question

Free demo downloads

Loading demo links...

Showing 1–3 of 10 questions

Question 1

DRAG DROP

Correctly arrange the sequence of the write operation in PowerStore.

Select and Place:

Answer is in the explanation below.

Question 2

A PowerStore X system is being implemented using Dell EMC S5248F-ON Ethernet switching as data switches.

What is required when configuring the VLT interconnects on the data switches?

Select an option, then click Submit answer.

  • ○

    Assign the switch default route for the VLT traffic

  • ○

    Set the VLT connection to the switch default VLAN

  • ○

    On each switch, select the switch management port MAC as the VLT MAC

  • ○

    Configure the VLT MACs with a matching unique made-up address

Question 3

When planning rack layout, why should base enclosures be grouped together?

Select an option, then click Submit answer.

  • ○

    Power distribution requirements

  • ○

    Rack weight balance

  • ○

    Ease of cable management

  • ○

    Hot aisle requirement