A project manager was just assigned to a new project. Which of the following activities should the project manager undertake after accepting the project? (Select TWO).
Select all that apply, then click Submit answer.
-
○
Review the detailed plan.
-
○
Develop a preliminary scope.
-
○
Develop a transition plan.
-
○
Develop a project management plan.
-
○
Review the resource pool.
-
○
Review the project objectives.