PK0-005 CompTIA Project+ Certification Exam

Loading demo links...

Showing 4–6 of 10 questions

Question 4

A project manager was just assigned to a new project. Which of the following activities should the project manager undertake after accepting the project? (Select TWO).

Select all that apply, then click Submit answer.

  • Review the detailed plan.

  • Develop a preliminary scope.

  • Develop a transition plan.

  • Develop a project management plan.

  • Review the resource pool.

  • Review the project objectives.

Question 5

A PM is responsible for implementing a new customer relationship management system and has learned that the sales organization is reluctant to utilize the new system. The organization's reluctance could jeopardize the success of the project. Which of the following steps should be taken to understand the adoption issues and gain organizational acceptance of the initiative? (Select TWO).

Select all that apply, then click Submit answer.

  • Train users on the proper use of the system.

  • Escalate the issue to the CCB

  • Hold sessions to understand user challenges.

  • Track system usage and report user activity.

  • Log the issue in the project risk register.

  • Create a memorandum of acceptable use.

Question 6

Due to budgetary and time constraints, a PM scheduled a meeting with all stakeholders during the planning phase to review the requirements and come to an agreement on the minimum viable product that would be acceptable. Which of the following would be used to document this input?

Select an option, then click Submit answer.

  • Project change management plan

  • Project management plan

  • Project transition plan

  • Project communication plan