A business analyst working on a project has identified:
3 requirements for which there is a workaround and the users can live without;
2 requirements that the users can live without for now;
15 requirements which, if not delivered, will make the solution unworkable or useless.
When these requirements are prioritized using MoSCoW, which of the following categories will not be used?
Select an option, then click Submit answer.
-
○
M
-
○
S
-
○
C
-
○
W