Free PRF – PRINCE2 Foundation Practice Test Question

Free demo downloads

Loading demo links...

Showing 4–6 of 15 questions

Question 4 (Volume A)

Which is a responsibility of a risk owner?

Select an option, then click Submit answer.

  • ○

    Identify risks to the project that might occur in their department

  • ○

    Own and authorize the use of the risk budget to fund risk responses

  • ○

    Manage, monitor and control all aspects of an assigned risk

  • ○

    Determine project risk appetite

Question 5 (Volume B)

Which is a purpose of an Exception Plan?

Select an option, then click Submit answer.

  • ○

    Show the reason for the tolerance deviation from a Stage Plan or Project Plan

  • ○

    Reduce the number of exception assessments, by agreeing a budget to cover the costs of any requests for change

  • ○

    Identify the actions required to recover from the effect of a tolerance deviation

  • ○

    Define the changes which are within the scope of the change budget

Question 6 (Volume A)

Which theme provides the controls to escalate any forecast beyond tolerance to the next management level?

Select an option, then click Submit answer.

  • ○

    Business Case

  • ○

    Plans

  • ○

    Progress

  • ○

    Quality