Question 10

All of the following are inputs to the quality process EXCEPT:

Select an option, then click Submit answer.

  • Organizational process assets.

  • Checklists.

  • Quality policy.

  • The project scope statement.


Question 11

Which of the following correctly explains the term "progressive elaboration"?

Select an option, then click Submit answer.

  • Changing project specifications continuously

  • Elaborate tracking of the project progress

  • Elaborate tracking of the project specifications with a change control system

  • Project specifications becoming more explicit and detailed as the project progresses


Question 12

What is included in a control chart?

Select an option, then click Submit answer.

  • Baseline

  • Planned value

  • Upper specification limit

  • Expenditure