CSSGB Six Sigma Green Belt

Loading demo links...

Showing 4–6 of 10 questions

Question 4

The generation of a Regression Equation is justified when we _____________. (Note: There are 4 correct answers).

Select all that apply, then click Submit answer.

  • Expect the relationship to be Linear between the output and inputs

  • Know that there is a non-linear relationship between output and input(s)

  • Need to understand how to control a process output by controlling the input(s)

  • Experience several process defects and have no other way to fix hem

  • When it is very expensive or too late to measure the output

Question 5

The reason(s) for not marking the customer Specification Limits (SL) on a Control Chart is which of these? (Note: There are 4 correct answers).

Select all that apply, then click Submit answer.

  • Process control teams should not control a process based on SLs

  • Displaying the SLs on a Control Chart sends a wrong signal toward process control

  • Marking the SLs on a Control Chart is against the principle of charting

  • By marking the SLs, one can confuse the operator as to what limits are critical

  • By using mere Control Limits the process only needs to be in Statistical Control

Question 6

What is the Cycle Time, in seconds, for a process having a Throughput of 7,200 units per hour?

Select an option, then click Submit answer.

  • 0.5

  • 2

  • 4

  • 10