Five original CAPM sample questions with worked answers across predictive, agile and business analysis topics, plus the truth about the passing score.

The passing-score question, answered honestly

Let us deal with the number first, because the internet will not: PMI does not publish a fixed percentage passing score for the CAPM exam. There is no official figure — not 61%, not 70%, not any other number — and any website stating one with confidence is guessing, recycling folklore, or both. PMI sets the passing standard using psychometric analysis of each exam form, and what you receive after the exam is a pass or fail decision plus a performance band for each domain: Above Target, Target, Below Target, or Needs Improvement.

This matters practically, not just pedantically. If you train against an invented percentage, you calibrate your readiness against fiction. Train instead to be consistently strong across all four CAPM domains — Project Management Fundamentals and Core Concepts, Predictive Plan-Based Methodologies, Agile Frameworks and Methodologies, and Business Analysis Frameworks — because the band report is how a failed attempt tells you exactly what to fix.

How the exam is built

As currently structured, the CAPM exam has 150 questions and a 3-hour time limit, delivered at a test centre or online with proctoring. It includes one 10-minute break, offered after you complete the first block of 75 questions; once you take that break and move on, you cannot return to the first block. The question mix reflects the current Exam Content Outline: roughly a third of the exam is agile, with business analysis carrying real weight alongside the traditional predictive material — a balance that surprises candidates who prepared from older, plan-driven-only study guides.

Five sample questions, worked properly

Each question below is original, written for this article. The point is not the answers themselves but the reasoning: notice how often the strongest wrong option is the one that sounds almost right.

Sample question 1. A sponsor signs a document that formally authorises the existence of a project and gives the project manager the authority to apply organisational resources to project activities. What is this document?

  • A. The business case
  • B. The project charter
  • C. The project management plan
  • D. The scope statement

Correct answer: B. The project charter is the document that formally authorises the project and names the project manager's authority. The business case (option A) is the strongest distractor because it also sits near the start of a project's life — but it justifies the investment decision; it is an input used to create the charter, not the authorising document itself. The project management plan (C) is developed after authorisation, and the scope statement (D) defines what will be delivered, not who is authorised to deliver it.

Sample question 2. At a status review, the planned value (PV) of the work scheduled is $40,000, and the earned value (EV) of the work actually accomplished is $32,000. What does this tell the project manager?

  • A. The project is under budget
  • B. The project is behind schedule
  • C. The project is ahead of schedule
  • D. The project is over budget

Correct answer: B. Schedule variance is EV minus PV: $32,000 − $40,000 = −$8,000. A negative schedule variance means less work has been accomplished than was planned for this point in time — the project is behind schedule. Option D is the trap: it feels like "we earned less than planned" should mean overspending, but cost performance requires the actual cost (AC), which this question never gives you. Without AC, no conclusion about budget is possible, which eliminates A and D together.

Sample question 3. During sprint planning, the development team asks who has the final say on the order of items in the product backlog. Who decides?

  • A. The Scrum Master
  • B. The project sponsor
  • C. The Product Owner
  • D. The development team lead

Correct answer: C. The Product Owner owns the product backlog, including the ordering of items by value. The Scrum Master (option A) is the strongest distractor because the role is deeply involved in every Scrum event — but the Scrum Master facilitates the process and coaches the team; prioritisation is not theirs to make. The development team (D) decides how much work it can pull into a sprint and how to build it, not the priority order, and the sponsor (B) funds the product without managing its backlog.

Sample question 4. A stakeholder insists that a requirement agreed early in the project has been missed in the delivered product. Which artefact should the project manager consult to trace that requirement from its origin through design, build, and testing?

  • A. The work breakdown structure
  • B. The requirements traceability matrix
  • C. The risk register
  • D. The stakeholder register

Correct answer: B. The requirements traceability matrix exists precisely for this: it links each requirement from its source through the deliverables and test results that satisfy it. The work breakdown structure (option A) is the tempting wrong answer because it also organises project work — but the WBS decomposes scope into deliverables and work packages; it does not record requirement lineage. The registers (C and D) track risks and stakeholders respectively, not requirements.

Sample question 5. Halfway through a sprint, an influential stakeholder asks the project manager to add a new feature immediately, outside the product backlog. What should the project manager do first?

  • A. Add the feature to the current sprint to keep the stakeholder satisfied
  • B. Refuse, explaining that changes are not permitted during a sprint
  • C. Discuss the request with the Product Owner so it can be assessed and prioritised
  • D. Escalate the request to the sponsor for a decision

Correct answer: C. The PMI mindset is to assess before acting, and to route work through the person who owns prioritisation — here, the Product Owner, who can evaluate the request's value and place it in the backlog where it competes fairly with other work. Option A corrupts the sprint's commitment and sets a precedent that the loudest voice wins. Option B is the rigid caricature of agile: changes are not forbidden, they are managed. Option D escalates before anyone has assessed impact, which skips the analysis step PMI expects first.

Using sample questions properly: pace, break, diagnose

One hundred and fifty questions in 180 minutes is 72 seconds per question, so CAPM pacing is steady rather than frantic — but scenario questions like sample question 5 take longer than recall items like sample question 1, and your practice should reproduce that mix. Take the mid-exam break when it is offered: it is the only scheduled pause, the first block is locked once you pass it, and a fatigued second half is where borderline candidates leak marks. Finally, score your practice by domain, not just in total. If your predictive answers are strong and your business-analysis answers are not, the band structure of the real result report is telling you in advance where your study hours belong — and timed, domain-scored free practice tests, including those on Study4Pass, make that diagnosis routine rather than guesswork. Before booking, confirm how much the CAPM exam costs, choose the best CAPM practice test you can find, and check how practice tests mirror the real exam so your rehearsal matches the real sitting.

CAPM Practice & Study Material

Related PMI Certifications

Share this guide X Facebook LinkedIn WhatsApp

Written by

Study4Pass Editorial Team

Study4Pass Editorial Team

The Study4Pass Editorial Team publishes practical IT certification study guides, exam breakdowns and preparation strategies based on the current exam objectives.